MATH TIME AND WORK

                                                            TIME AND WORK
          Basically  
                         TIME(T)   is  directly propotional to WORK(W).
             Time  means ,time required to complete the work .Lets take example for a man in less time(no of days) ,he will perform less amount of work  and vice versa.
   Comaprision of two scenario::
         M1 D1 H1/W1 R1=  M2 D2H2/W2 R2
             WHERE  M=  stands for no of person
                    D=  no of days
                   H= no of hours
                   W= total work
                   R= rate($)
          HOW TO SOLVE THE QUESTION :: choose any method for solving the question
Method 1::    by one day concept:
                         Example:  IF A can do work in 10 days and B can do work in 15 days.Then how many days    required if they work together?.
                         Description: in this method  days are   converted into 1 days work  i.e.
                          A one days work =1/10 (because normally in  1 day he will do only 1/10 part of total work)
                          similarly     B  one day work=1/15
                        then both A   and  B   1 day  work = 1/10 +1/15
                                                                                    =3+2/30 
                                                                                    =5/30
                                                                                   =1/6
                                      Thus both A  and B  together can finish 1/6 part of work in one day .Now just reverse it to find total no of days to finish the work   i.e.  6 days.
                        
Method 2:: by LCM concept:
                           Example:  IF A can do work in 10 days and B can do work in 15 days.Then how many days    required if they work together?.
                             Description: in this method LCM will take for days  then based upon total work each person per work day is calculated  i.e


                             Now   total work done by A and B =3w/d+ 2w/d
                                                           =5w/d
                                                            Person A and B  will do 5 work per day of total work 30.
                                                      5   work can do work in --------> 1 day
                                                    30  work can do work in ------- >   30/5 day
                                                                                              -------- > 6 days

                                                                   QUESTION
QUESTION 1:  A ,B  can do work in 12 days  and   B,C  can do work in 15 days   and A,C can do in 20 days  .In how many days together A,B,C can finish work ?.
Solution:          (A + B)    1 day work=1/12
                        ( B+C)    1 day work=1/15
                       (C+A )    1 day work=1/20
                Add above 3 equation
                              2(A+B+C)   one day work = (1/12)+(1/15)+(1/20)
                              2(A+B+C)   one day work  =(5+4+3)/60
                               2(A+B+C)   one day work =12/60
                              2(A+B+C)   one day work= 1/5
                                (A+B+C)   one day work=1/10
              Thus total work will be finish in 10 days.
QUESTION 2:  If 10 men complete quater work in 12 days when they work 8 hours per day,In how many days 18 men  complete the full work when they work 6 hours  per day ?. 
Solution:             M1 D1 H1/W1 =  M2 D2H2/W2
                                         (10*12*8)/(1/4)  =18* d *6/1
                                          d=10*12*8*4/18*6
                                          d=320/9  days