TIME AND WORK
Basically
TIME(T) is directly
propotional to WORK(W).
Time means ,time required to complete the work
.Lets take example for a man in less time(no of days) ,he will perform less
amount of work and vice versa.
Comaprision of
two scenario::
M1 D1 H1/W1 R1= M2 D2H2/W2
R2
WHERE M= stands for no of person
D= no of days
H= no of hours
W= total work
R= rate($)
HOW TO SOLVE THE QUESTION ::
choose any method for solving the question
Method 1:: by
one day concept:
Example: IF A can do
work in 10 days and B can do work in 15 days.Then how many days required if they work together?.
Description: in this method
days are converted into 1 days
work i.e.
A one days work =1/10 (because normally in 1 day he will do only 1/10 part of total
work)
similarly B
one day work=1/15
then both A and
B 1 day work = 1/10 +1/15
=3+2/30
=5/30
=1/6
Thus both
A and B
together can finish 1/6 part of work in one day .Now just reverse it to
find total no of days to finish the work
i.e. 6 days.
Method 2:: by
LCM concept:
Example: IF A can do work in 10 days and B can do work
in 15 days.Then how many days required
if they work together?.
Description:
in this method LCM will take for days
then based upon total work each person per work day is calculated i.e
Now total work done by A and B =3w/d+ 2w/d
=5w/d
Person A and B will do 5 work per
day of total work 30.
5 work can do work in
--------> 1 day
30 work can do work in -------
> 30/5 day
-------- > 6 days
QUESTION
QUESTION 1: A ,B can do work in 12 days and
B,C can do work in 15 days and A,C can do in 20 days .In how many days together A,B,C can finish
work ?.
Solution: (A +
B) 1 day work=1/12
( B+C) 1 day work=1/15
(C+A ) 1 day work=1/20
Add above 3 equation
2(A+B+C) one day work = (1/12)+(1/15)+(1/20)
2(A+B+C) one day work
=(5+4+3)/60
2(A+B+C) one day work =12/60
2(A+B+C) one day work= 1/5
(A+B+C) one day work=1/10
Thus total work will be finish in
10 days.
QUESTION 2: If
10 men complete quater work in 12 days when they work 8 hours per day,In how
many days 18 men complete the full work
when they work 6 hours per day ?.
Solution:
M1 D1 H1/W1 = M2 D2H2/W2
(10*12*8)/(1/4) =18* d *6/1
d=10*12*8*4/18*6
d=320/9 days
No comments:
Post a Comment